Multi-process Marking and Facade Project of Huailu Interchange in Jinhua, Zhejiang
 | Construction Time:November 16, 2023
Construction Temperature:24℃
Construction Materials:SW402-03 SL002
Sprinkling Process:Pneumatic Surface-sprinkled Glass Beads |
Construction Notes
The construction was carried out throughout the day with a short construction period, and the road closure time was only 24 hours.
Graco 300-type hand cart was used, which featured beautiful line shape, low failure rate and high construction efficiency.
The daytime temperature was comfortable, while the ambient temperature at night was relatively low, so 2% curing agent was added.
The retroreflection coefficients of the marking lines and vertical surface spraying were tested in real time.